milestone action type

In the Milestone Statuses by Project report (Projects application), you can view all of a selected project's actions that have been assigned the Activity Type of Project-Milestone. You can assign the Activity Type Project-Milestone when you add or edit an action.

Typically, milestones are assigned a duration of 0 or 1 day; their start date and end dates are always the same value. Milestones appear on the Gantt chart as a diamond.

See action type .