Schedule Performance Index
Schedule Performance Index
In the Projects application, the Schedule Performance Index is displayed in various reports.
Schedule Performance Index = Budgeted Cost of Work Performed/Budgeted Cost for Work Scheduled
>1 indicates ahead of schedule
<1 indicates behind schedule
In the equation above, the Budgeted Cost of Work Performed is based on the design cost estimates.