Schedule Performance Index

In the Projects application, the Schedule Performance Index is displayed in various reports.

Schedule Performance Index = Budgeted Cost of Work Performed/Budgeted Cost for Work Scheduled

>1 indicates ahead of schedule

<1 indicates behind schedule

In the equation above, the Budgeted Cost of Work Performed is based on the design cost estimates.