Status Reports
Capital Projects / Projects
Status Reports
The Monitor process includes the following status reports. For each of these reports, you can generate a report by clicking the DOC button, or export data to Excel by clicking the XLS button.
- Project Statuses : The Project Statuses report displays the project type, status, contact, and description for each current project.
- Work Package Statuses: In the Work Package Statuses report, you can view the status and description for all current work packages for a selected project.
-
Milestone Statuses by Project
: In the Milestone Statuses by Project, you can view all of a selected
project's actions that have been assigned the Action Type of Project-Milestone, and that have a duration of one day. Project Milestones are displayed differently on the Gantt Chart by using the Milestone icon.
Note : You can assign the Action Type Project-Milestone when you add or edit an action.
-
Projects Behind Schedule
: In this report, the projects that are behind schedule (Schedule Performance
Index <1) are displayed. The Schedule Performance Index is calculated
as Budgeted Cost of Work Performed/Budgeted Cost for Work Scheduled.
If you click on a project in the left panel, a detail report on actions that are overdue is displayed in the right panel.
- Projects Over Budget : In this report, the projects that are over budget (Cost Performance Index <1) are displayed. Cost Performance Index is calculated as Budgeted Cost of Work Performed/Actual Cost of Work Performed. Select an over-budget project in the left panel, and details for its completed actions are shown in the right panel.